CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Coram 1. Dr. Pramod Deo, Chairperson 2. Shri R.Krishnamoorthy, Member 3. Shri S.Jayaraman, Member 4. Shri V. S. Verma, Member Petition No 106/2009 (Suo-motu) In the matter of
Maintenance of Grid Discipline – Non -compliance of provisions of the Indian Electricity Grid Code by Tamil Nadu Electricity Board. Petition No 130/2009 (Suo-motu) In the matter of
Maintenance of Grid Discipline – Non -compliance of provisions of the Indian Electricity Grid Code by Tamil Nadu Electricity Board during May 2009 And in the matter of
Tamil Nadu Electricity Board,
The following were present:
1. Shri P Soma Sundaram, Advocate, TNEB 2. Shri V Chandran, TNEB 3. Shri. V. Suresh, SRLDC, 4. Shir. M. L. Batra, SRLDC
(Date of Hearing 30.7.2009)
On receipt of report from the Southern Regional Load Despatch Centre
(SRLDC), the Commission, vide its order dated 12.6.2009 in Petition No.
106/2009 (suo motu) directed the respondent to show cause as to why it should
not be held guilty of contravention of and non-compliance with the provisions of
clauses 5.4.2 and 6.4.7 of the Indian Electricity Grid Code (Grid Code) for over-
drawl of electricity at frequency below 49.2 Hz. The respondent was also directed
to explain as to why penalty under Section 142 of the Electricity Act, 2003 (the
Act), be not imposed on it for over-drawl of electricity as aforesaid during each
time-block during the period 10.4.2009 to 10.5.2009. A similar notice dated
2.7.2009 for over-drawal during the period 25.5.2009 to 31.5.2009 was also
issued in Petition No. 130/2009 (suo motu). This notice in addition pointed out
violations by the respondent of clause (1) of Regulation 7 of the Central
Electricity Regulatory Commission (Unscheduled Interchange charges and
related matters) Regulations, 2009 (the UI charges regulations) by over-drawing
in excess of 12% of its scheduled drawal or 150 MW (whichever is lower) when
frequency was below 49.5 Hz. The necessary details of over-drawals were
The respondent filed its separate replies (dated 26.6.2009 and 21.7.2009)
to the show cause notices. We have gone through these replies and heard the
learned counsel of the respondent and its representative.
Before we deal with the respondent’s submissions on merits, we propose
to consider certain legal issues raised by the respondent in the replies to the
According to the respondent, sub-section (5) of Section 29 of the Act
provides that any dispute between the Regional Load Despatch Centre (RLDC)
and the State transmission licensee is to be referred to the Commission.
Therefore, it has been urged, the Commission is not empowered under the law
to initiate suo motu proceedings under Section 142 of the Act for alleged
violation of the Grid Code, particularly so when Section 29 of the Act specifically
provides for penal action for violation of directions of the Regional Load
In our opinion the objection is without any substance. The proceedings
were initiated against the respondent on the ground of contravention of
provisions of the Grid Code specified by the Commission in exercise of powers
under Section 178 of the Act. By virtue of provisions of Section 142 of the Act,
the Commission is empowered to take appropriate proceedings either on the
basis of a complaint made by any person affected by the non-compliance of the
Act, rules or regulations made thereunder or by the Commission on its own. Non-
compliance of the directions of the Regional Load Despatch Centre made
punishable under sub-section (6) of Section 29 of the Act is a separate and
distinct offence. Therefore, even though the proceedings have been started
based on reports from the Southern Regional Load Despatch Centre, these
proceedings are maintainable under Section 142 of the Act as subject matter of
the show cause notices essentially relate to contravention of the provisions of the
Grid Code, which is statutory in nature.
The respondent has further submitted that competency of the Commission
to initiate suo motu proceedings is sub judice in the Writ Petition No 10384/2009
before the Madras High Court who has issued a stay order in an earlier
proceeding taken against the respondent under similar circumstances. In view of
this, the respondent has pleaded, it is appropriate that the Commission defers
the proceedings till a final verdict is given by the Hon’ble High Court.
It bears notice that the Civil Writ Petition No 10384/2009 has been filed by
the respondent before Madras High Court against the Commission’s order dated
8.5.2009 in suo motu proceedings in Petition No. 81/2009. The Hon’ble High
Court has passed the order dated 15.6.2009 as under -
“Writ petitions under Article 226 of the Constitution of India praying that in the circumstances stated therein and in the respective affidavits filed therewith the High Court will be pleased to (i) issue a Writ of Certiorari calling for the entire records of the respondents relating to the order dt 8.5.2009 in suo motu petition No. 81/2009 and quash the same [in WP. No/ 10384/09] and (ii)
Stay all further proceedings pursuant to the order of the respondent
dated 8.5.2009 in Suo Motu Petition No. 81/2009 [ in MP. No. 1/09] pending WP. No. 10384/09 respectively. Order : These petitions coming on for orders upon perusing the petitions and the respective affidavits filed in support thereof and upon hearing the arguments of M/s. P. Srinivas, Advocate for the petitioner in both the petitions, the court made the following order:-
A bare reading of the said order reveals that it is based on the
circumstances stated in the writ petition and the affidavits of the respondent. The
stay order of the Hon’ble High Court cannot be said to be an order in rem. In fact,
no suggestion to that effect is made in the reply by the respondent. And nothing
was so suggested at the hearing. We are satisfied that the interim order of the
Hon’ble High Court or the fact of pendency of the writ petition do not, in any
manner, interdict the Commission in discharge of its statutory responsibilities of
It has been next urged by the respondent that clauses 5.4.2 and 6.4 of the
Grid Code whose violation has been alleged in the show cause notices, call upon
the utilities to “endeavour” to restrict their net drawal from the grid. The argument
made is that so long as the respondent attempted to curtail over-drawal – it is the
case of the respondent that it made efforts to curtail over-drawal - and,
therefore, it cannot be proceeded against.
The argument made is too naïve to merit any serious consideration. For
proper understanding it may be appropriate to have a look at the statutory
provisions and accordingly they are extracted hereunder -
“5.4.2 Manual Demand Disconnection (a) As mentioned elsewhere, the constituents shall endeavour to restrict their net drawal from the grid to within their respective drawl schedules whenever the system frequency is below 49.5 Hz. When the frequency falls below 49.2 Hz, requisite load shedding (manual) shall be carried out in the concerned State to curtail the over-drawal.” 6.4 Demarcation of responsibilities ………………. 7. Provided that the States, through their SLDCs, shall always endeavour to restrict their net drawal from the grid to within their respective drawal schedules, whenever the system frequency is below 49.5 Hz. When the frequency falls below 49.2 Hz, requisite load shedding shall be carried out in the concerned State(s) to curtail the over-drawal.”
Under the above extracted provisions, which are identically worded, the
actions required to be taken by the utilities over-drawing electricity from the
regional grid are that they are mandated to
endeavour or make efforts to limit their over-drawal when frequency
resort to “requisite” load-shedding when frequency is below 49.2
The purpose of the above provisions is that the frequency be restored to
the normative level of 49.5 Hz. Although load-shedding is not mandatory
immediately after fall of frequency below 49.5 Hz, this so when the frequency
falls below 49.2 Hz as evidenced by use of the word “shall” in the second leg of
the provision. The submission that the provisions of the Grid Code consciously
employ the word “endeavour” and thereby the utilities concerned are required
only to “attempt” to restrict over-drawal, seems to be a deliberate effort to evade
The result of the above discussion is that the preliminary objections urged
by the respondent on the maintainability of the show cause notices stand
rejected. This leads to consideration of the respondent’s claim on merits. The
submissions made on merits are generally common in the two replies filed by the
14. The respondent while seeking discharge of the notice issued under
Section 142 of the Act has not denied the fact of over-drawals given in the show
cause notices dated 12.6.2009 and 2.7.2009. The respondent has sought to
justify its over-drawals by stating that demand increased due to extreme hot
weather conditions, lack of any significant capacity addition in the State,
parliamentary elections, low generation at the atomic power stations in the region
due to fuel shortage, forced outages of the State and Central sector generating
units, and uncertainty of wind generation which, according to the respondent,
contributes 15% to 20% of peak demand during wind season. The respondent
has stated that it had since 1.11.2008 taken various Load Management
measures in the State which include imposition of power cut of 40% on the HT
industries and commercial establishments and 20% on LT-CT industries and
commercial consumers, restricting power supply to the farmers, load-shedding
for 2 hours in rotation on urban and rural feeders, carrying out of tripping of
additional 110 kV feeders, and procuring power round the clock from other States
and through Power Exchange at a high cost. The respondent has further stated
that its fair expectation of other constituents picking up their standby generation
when there was fall in the regional frequency due to drop in wind generation, did
15. In its reply affidavit in Petition No. 130/2009, the respondent has urged
certain additional pleas. It has been stated that NEW Grid frequency prevailed at
comfortable level in many blocks during 25.5.2009 to 30.5.2009 and was even
going beyond 50.2 Hz. Under these circumstances, the respondent has stated,
non-availing the UI support might have pushed NEW Grid frequency beyond the
operational band. the respondent has claimed to have under drawn from the grid
on 28.5.2009 and 29.5.2009and that in many time blocks over-drawal was when
the frequency was just hovering around 49.5 Hz.
We are not impressed by the extenuating circumstances or the corrective
measures narrated by the respondent. It is pointed out that there is nothing new
in the pleas taken by the respondent in reply to the show cause notices .Similar
pleas were taken in the past in the proceedings initiated by the Commission. The
replies are generally the replica of the replies filed by the respondent in response
to the earlier proceedings. Therefore, we do not intend to deal with each of these
pleas in great detail. Hot weather conditions, parliamentary elections, low
generation at the atomic power stations in the region are not the factors specific
to the respondent. They were common to all the constituents in the region. The
other constituents facing similar difficulties were entitled to draw as per the
schedule. Even that was prevented because of reckless over-drawal by the
respondent. We are of the considered view that these factors cannot provide
valid justification for over-drawal by the respondent at the cost of other regional
constituents. Under the extreme situations of power scarcity, adherence to the
schedule was the primary responsibility of the respondent as over-drawal did not
provide any solution to overcome shortage situation. Drawal of other
constituents’ share particularly when frequency was low, cannot be viewed
leniently under any circumstances. The respondent reportedly took some
measures to curtail its demand. These measures proved totally inadequate for
the reason that over-drawals continued at frequency which could be termed as
sub-optimal. Thus, over-drawal under the circumstances does not absolve the
respondent of its responsibility to adhere to the statutory provisions or a licence
to flout them with impunity. We wish to emphasize that neither the Grid Code nor
the UI charges regulations provide for any leniency in case of over-drawal under
the circumstances relied upon by the respondent.
Based on the above, we hold the respondent guilty of contravention of and
non-compliance with the provisions of clauses 5.4.2(a) and 6.4.7 of the Grid
Code during the periods 10.4.2009 to 9.5.2009 and 25.5.2009 to
31.5.2009.Besides, the respondent is found guilty of violation of clause (1) of
Regulation 7 of the UI charges regulations also during 25.5.2009 to 31.5.2009.
The next question is regarding the penalty to be levied on the respondent
after it has been found guilty of contravention of and non-compliance with the
provisions of the Grid Code and the UI charges regulations. According to the
respondent, even in the proceedings under Section 142, penalty is to be imposed
only after considering the conditions specified in Section 144.
The respondent’s contention that the conditions prescribed in Section 144
of the Act are to be considered in the proceedings before imposition of penalty
under Section 142 is manifestly untenable. Section 144 applies to the
adjudication proceedings before the adjudicating officer appointed under Section
143 of the Act for inquiry into instances of default or non-compliance of directions
of the Regional Load Despatch Centre issued under Section 29 of the Act.
Inasmuch that the present proceedings by the Commission are under Section
142, strictly there is no need to have any recourse to Section 144. However, at
the instance of the respondent we propose to examine applicability of the
principles provided in Section 144 of the Act to the facts of the proceedings
In terms of Section 144, the adjudicating officer appointed under Section
143 of the Act is enjoined to have due regard to the following factors while
adjudicating on the quantum of penalty, namely,
the amount of disproportionate gain or unfair advantage, wherever quantifiable, made as a result of the default;
In the past, the respondent has been found guilty of contravention of and
non-compliance with the provisions of the Grid Code on several occasions.
Proceedings in Petitions No 137/2008 and 81/2009 are just two instances of
violation of the Grid Code. Thus, the contraventions for which the present
proceedings have been taken are of repetitive nature. The respondent has
certainly been beneficiary of the defaults committed. The acts of the respondent
have caused wrongful loss to other constituents in the region and their
consumers inasmuch as they have been deprived of the opportunity to supply
power to their own consumers. However, it may not always be possible to
quantify with any degree of exactitude the extent of unlawful advantage drawn by
the respondent on account of such over-drawals. But the respondent has
certainly drawn the advantage since otherwise it would not have resorted to over-
drawals of high magnitude, the details of which are given in the show cause
notices. Thus, even though it is not necessary to invoke provisions of Section
144 in the present proceedings, their application at the insistence of the
respondent does not come to its rescue. .
The respondent has further submitted that imposition of maximum penalty
of Rs. one lakh multiplied by the number of time blocks is patently illegal and
The respondent’s submission in this regard is not supported by any
rationale and lacks any legal force. For the purpose of grid frequency
management, each day has been divided into 96 time-blocks of 15 minutes
duration. In this fashion, each time-block constitutes a separate unit, Therefore,
depending upon the facts and circumstances of each case, the maximum penalty
prescribed under the law can be imposed separately for each contravention. For
the reasons already recorded, we feel that the respondent, for the contraventions
forming the basis of the present proceedings does not deserve any indulgence
and penalty not less than the maximum of the penalty for each contravention will
be justified. However, for this purpose, we have decided to exclude the instances
of over-drawal up to 150 MW during a time-block indicated in the show cause
notices.There are 335 instances of such over-drawals during 10.4.2009 to
10.5.2009 and 102 (as given in the show cause notice dated 2.7.2009) such
instances during 25.5.2009 to 31.5.2009.
Accordingly, we direct that penalty at the rate of Rs one lakh for each of
the time-blocks listed in the Commission’s orders dated 12.6.2009 and 2.7.2009,
where over-drawals were more than 150 MW (total 335+102 = 437) be imposed
on the respondent. The details of such instances are contained in Annexure I
and Annexure II attached to this order. The total penalty works to Rs. 4.37 crore.
The penalty shall be deposited latest by 31.8.2009.
With the above order, the present proceedings stand disposed.
[V. S. VERMA] [S. JAYARAMAN] [R. KRISHNAMOORTHY] [DR. PRAMOD DEO] MEMBER MEMBER CHAIRPERSON New Delhi, dated 21st August 2009 Annexure I Details of over-drawals during 10.4.2009 to 10.5.2009 in excess of schedule by more than 150 MW. BLOCK NO. Over Drawl (Avg. MW) Annexure II Details of over‐drawals during 25.5.2009 to 31.5.2009 in excess of schedule by more than 150 MW.
Asked by I come from a land locked place (in Canada) where there are no oceans around and just lakes. Whenever I go on a boat in a lake in Canada, I never get seasick and I feel fine. Sometimes when Icome to a place like Mexico and I go out on the ocean, I get sea sick easily while others feel fine. Iwas wondering if getting sea sick can be caused by not being used to being out on the ocean wheret
Substance Abuse and Addiction Course Rationale Throughout history, cultures have used psychoactive drugs for various Unit V purposes such as recreation, rituals, ceremonies, and medicinal purposes. A major concern for today’s medical professionals is substance abuse and its effect on society. To live a healthy lifestyle throughout one’s lifespan an understanding of the re